INDUSTRY NEWS

More Industry News

FEATURED PRODUCTS

MT20T-12-C-1.2-460Ac MT20T-12-C-1.2-460Ac
MT20T-12-C-1.2-460Ac Trunnion with position feedback for machine control application
On-Site Laser Data Collection
Turbine Field Engineers using REACT in-house manufactured laser equipment, collect Laser Alignment readings providing accurate, repeatable component positions
Pike Poles Pike Poles
Pike Poles were designed to aid the practical person in the field using pole line tools
Metal Bellows-Type Seal Metal Bellows-Type Seal
The new TDGS elastomer-free, high-efficiency, gas-lubricated seal is well suited for use in single-stage
More Featured Products

REGULATORY NEWS

  • ABB Showcases Investment In Solar Technology

    ABB is unveiling new solar power conversion and energy storage devices and solutions at this year’s Solar Power International event.

  • Eguana Completes Distribution Agreement For German Product Launch

    Eguana Technologies Inc (TSX-V:EGT) (OTCQB:EGTYF), one of the leaders in power conversion and control systems for distributed energy storage is pleased to announce it has completed a distribution agreement with German distributor Technologietransfer & Marketing GmbH ("Tt&M") (www.ttmarket.com)

  • ABB Software Solution To Improve Outage Response At Major U.S. Utility

    ABB has successfully delivered its latest distribution and outage management systems to ComEd, a unit of Chicago-based Exelon Corporation, the United States’ leading energy provider. The software solution helps ComEd minimize the impact of outages for its customers across northern Illinois.

  • ABB Wins $30M Order To Strengthen Power Infrastructure In Iraq

    ABB has won an order to supply and install a substation at the 3,000 megawatt (MW) Rumaila power plant, located in the Basra region of southern Iraq. The completed power plant will be operated by Shamara Holding Group (SHG), one of Iraq’s largest private industrial conglomerates and an independent power producer

  • NGCP Energizes Repaired Ormoc 150MVA Transformer

    At 10:32 PM on July 29, NGCP energized its 150MVA Transformer 1 at its Ormoc Substation. The said transformer is now in parallel operations with the 150MVATransformer 2 (energized on July 28) and 150MVA Transformer 3 (energized on July 13).  This is over and above its earlier July 31 commitment to energize just 2 transformers.

  • Siemens Receives Major Order From TenneT For DolWin6 Offshore Grid Connection

    Siemens has received another order from the German-Dutch grid operator, TenneT TSO, for a grid connection for offshore wind power plants in the German waters of the North Sea. The company will supply the entire technology for efficient direct-current transmission for the "DolWin6" grid connection

More Regulatory News

TRADING NEWS

  • ABB Showcases Investment In Solar Technology

    ABB is unveiling new solar power conversion and energy storage devices and solutions at this year’s Solar Power International event.

  • Eguana Completes Distribution Agreement For German Product Launch

    Eguana Technologies Inc (TSX-V:EGT) (OTCQB:EGTYF), one of the leaders in power conversion and control systems for distributed energy storage is pleased to announce it has completed a distribution agreement with German distributor Technologietransfer & Marketing GmbH ("Tt&M") (www.ttmarket.com)

  • ABB Software Solution To Improve Outage Response At Major U.S. Utility

    ABB has successfully delivered its latest distribution and outage management systems to ComEd, a unit of Chicago-based Exelon Corporation, the United States’ leading energy provider. The software solution helps ComEd minimize the impact of outages for its customers across northern Illinois.

  • ABB Wins $30M Order To Strengthen Power Infrastructure In Iraq

    ABB has won an order to supply and install a substation at the 3,000 megawatt (MW) Rumaila power plant, located in the Basra region of southern Iraq. The completed power plant will be operated by Shamara Holding Group (SHG), one of Iraq’s largest private industrial conglomerates and an independent power producer

  • NGCP Energizes Repaired Ormoc 150MVA Transformer

    At 10:32 PM on July 29, NGCP energized its 150MVA Transformer 1 at its Ormoc Substation. The said transformer is now in parallel operations with the 150MVATransformer 2 (energized on July 28) and 150MVA Transformer 3 (energized on July 13).  This is over and above its earlier July 31 commitment to energize just 2 transformers.